We Will Be Done When?
1/18/2005 1:01:00 PM
We have a schedule in writing. More good news: The contractor thinks we will be done by the end of this June! He claims this includes the rain delays we have had the past month too.
Slideshow:  It's a Date! We were originally told it would take 9-11 months so we have been thinking 12 months or more ever since demolition started at the end of August. Most importantly it gives us a real date for our planning. Oh yes, we are aware that there could (and probably will) be slippage along the way but we always like good news.

If you want to see a schedule breakdown by skill (framing, roofing, stucco, etc.) please view the slideshow.