The Slow Buildup - Can We Pour the Footings Yet?
10/17/2004 12:00:00 PM
After 2 weeks of continual work we may be ready to pour next week. The contractor reports that we passed our first inspection so we've jumped that hurdle. We are tired of things coming down and are anxious for the building up process to begin.
Slideshow:  Can we pour now? Things always take longer when you don't know what to expect. The concrete guys have been here every day for the last 2 weeks, but we aren't quite ready to pour the concrete yet. Just a few more days if the weather cooperates. Not much hope of that. Showers are forecast for the next few days.

The pictures show lots of rebar and the framing for the footings. There's also a picture of the storage tanks we'll use for cisterns