8/17/2005 9:00:00 PM
Some of the kitchen cabinets are installed
  1. The outline is there
  2. we can see the island
  3. there's even a leg for the island
  4. bathroom cabinets are also installed
Slideshow:  a Kitchen! All of the lower cabinets are installed. We are waiting for the granite to appear. We expect that to happen around 8/25.

All of the rooms except the kitchen have their full paint allotment. It almost looks livable.

The final stucco coat has been applied. After 2-3 weeks curing time we'll see the final paint coat.

Hardwood floors are appearing. The living room is mostly done now. Should be done by 8/25.

Tile for bathrooms and stairs are due to start this week. They expect a quick completion. Right!