All of the lower cabinets are installed. We are waiting for the granite to
appear. We expect that to happen around 8/25. All of the rooms except the
kitchen have their full paint allotment. It almost looks livable.
The final stucco coat has been applied. After 2-3 weeks curing time we'll see
the final paint coat.
Hardwood floors are appearing. The living room is mostly done now. Should be
done by 8/25.
Tile for bathrooms and stairs are due to start this week. They expect a quick
completion. Right! |